A nine-hour plan requires real parallel resources
Read the illustration’s labels
TASK
HOURS
MUST FOLLOW
A: assess
1
Start
B: clear
2
A
C: obtain parts
3
D: repair bench
B
E: assemble
C and D
F: inspect
E
Time from start / hours
In the drawing: TASK HOURS MUST FOLLOW; A: assess 1 Start; B: clear 2 A; C: obtain parts 3 A; D: repair bench 3 B; E: assemble 2 C and D; F: inspect 1 E; Time from start / hours
Critical path: A B D E F = 9 hours
C ends at hour 4; E needs it by hour 6: 2 hours slack.
If one worker must do every task without overlap: 1 + 2 + 3 + 3 + 2 + 1 = 12 hours.
Original teaching drawing · Numerical examples are invented
All durations are invented. Nine hours assumes compatible parallel resources; a single worker performing every task needs twelve task‐hours without overlap.
A schedule must distinguish the time a task takes from the time it can begin. In the invented example, task A is assessment, lasting one hour. B is clearing the work area, two hours after A. C is obtaining the approved parts, three hours after A. D is repairing a noncritical bench, three hours after B. E is assembly, two hours after both C and D. F is inspection, one hour after E.
If the required people and resources can genuinely work in parallel, A ends at hour one. B ends at hour three, while C ends at hour four. D then ends at hour six. Assembly cannot begin when the parts arrive at hour four because the bench is not ready; it begins at hour six and ends at eight. Inspection ends at nine.
The chain ABDEF therefore controls the ninehour earliest completion in this simplified model. It is the critical path under the stated durations and resource assumptions. The parts branch can finish two hours later than planned without delaying E, provided nothing else changes. That allowance is schedule slack, not permission to ignore uncertainty or move the delivery indefinitely.
Now remove the parallelresource assumption. If one person must perform every task and no work can overlap, the total task time is twelve hours. The same dependency graph does not create another worker. A useful plan therefore names the responsible person or team, equipment and location as well as the predecessor task.
Review the plan after real observations. A duration estimate may change when the item is inspected. A delivery promise may slip. Record the changed assumption and recompute the affected sequence. Avoid updating only the final promised date while leaving an impossible internal plan untouched. A clear schedule shows why work waits and where a useful intervention can actually shorten the wait.
A / B / C / D / E / F ‐ Task identifiers in the schedule. Letters identify the six invented tasks; they do not abbreviate task names. F‐F on a drawing instead identifies a section view.
The slowest station and the same worker are different limits
Plan the order of work and the capacity to do it
Units and terms in this account
= equals
min minute, 60 seconds