A nine-hour plan requires real parallel resources

Read the illustration’s labels

TASK

HOURS

MUST FOLLOW

A: assess

1

Start

B: clear

2

A

C: obtain parts

3

D: repair bench

B

E: assemble

C and D

F: inspect

E

Time from start / hours

In the drawing: TASK HOURS MUST FOLLOW; A: assess 1 Start; B: clear 2 A; C: obtain parts 3 A; D: repair bench 3 B; E: assemble 2 C and D; F: inspect 1 E; Time from start / hours

Critical path: A B D E F = 9 hours

C ends at hour 4; E needs it by hour 6: 2 hours slack.

If one worker must do every task without overlap: 1 + 2 + 3 + 3 + 2 + 1 = 12 hours.

Original teaching drawing · Numerical examples are invented

All durations are invented. Nine hours assumes compatible parallel resources; a single worker performing every task needs twelve task‐hours without overlap.

A schedule must distinguish the time a task takes from the time it can begin. In the invented example, task A is assessment, lasting one hour. B is clearing the work area, two hours after A. C is obtaining the approved parts, three hours after A. D is repairing a noncritical bench, three hours after B. E is assembly, two hours after both C and D. F is inspection, one hour after E.

If the required people and resources can genuinely work in parallel, A ends at hour one. B ends at hour three, while C ends at hour four. D then ends at hour six. Assembly cannot begin when the parts arrive at hour four because the bench is not ready; it begins at hour six and ends at eight. Inspection ends at nine.

The chain ABDEF therefore controls the ninehour earliest completion in this simplified model. It is the critical path under the stated durations and resource assumptions. The parts branch can finish two hours later than planned without delaying E, provided nothing else changes. That allowance is schedule slack, not permission to ignore uncertainty or move the delivery indefinitely.

Now remove the parallelresource assumption. If one person must perform every task and no work can overlap, the total task time is twelve hours. The same dependency graph does not create another worker. A useful plan therefore names the responsible person or team, equipment and location as well as the predecessor task.

Review the plan after real observations. A duration estimate may change when the item is inspected. A delivery promise may slip. Record the changed assumption and recompute the affected sequence. Avoid updating only the final promised date while leaving an impossible internal plan untouched. A clear schedule shows why work waits and where a useful intervention can actually shorten the wait.

A / B / C / D / E / F ‐ Task identifiers in the schedule. Letters identify the six invented tasks; they do not abbreviate task names. F‐F on a drawing instead identifies a section view.

The slowest station and the same worker are different limits

Plan the order of work and the capacity to do it

Throughput, first-item time and one-person work differ

Read the illustration’s labels

PREPARATION

15 min / item 4 per

hour

ASSEMBLY

30 min / item 2 per

INSPECTION

20 min / item 3 per

In the drawing: PREPARATION; 15 min / item 4 per hour; ASSEMBLY; 30 min / item 2 per hour; INSPECTION; 20 min / item 3 per hour

Bottleneck

Read the illustration’s labels

MODEL

RESULT

Independent stations

Steady-state limit: 2 items / hour

One item, no waiting

15 + 30 + 20 = 65 minutes

One worker, no overlap

60 / 65 ≈ 0.923 item / hour

First-pass quality

10 / 12 ≈ 83.33%

Time availability

6.5 / 8 = 81.25%

These are distinct measures. Do not average them into one claim.

In the drawing: MODEL RESULT; Independent stations Steady-state limit: 2 items / hour; One item, no waiting 15 + 30 + 20 = 65 minutes; One worker, no overlap 60 / 65 ≈ 0.923 item / hour; First-pass quality 10 / 12 ≈ 83.33%; Time availability 6.5 / 8 = 81.25%; These are distinct measures. Do not average them into one claim.

Invented station times, independent staffing and no transfer losses. The one‐worker comparison and the first‐item processing time use different, explicitly stated models.

Capacity describes a rate under stated conditions. It should not be confused with the elapsed time of one job. In the invented line, preparation takes fifteen minutes per item, assembly thirty and inspection twenty. With independent adequately staffed stations, preparation can handle four items per hour, assembly two and inspection three. Assembly is the limiting station at two items per hour in this simplified steadystate calculation.

One item still needs sixtyfive minutes of processing across the three operations, before transfer or waiting time. The line does not complete the first item in thirty minutes merely because its steadystate bottleneck rate is two per hour. A diagram that reports only the fastestlooking number hides this distinction.

If one person performs all three operations, the relevant processing total is sixtyfive minutes per item. The idealized rate is sixty divided by sixtyfive, approximately 0.923 item per hour. Adding another machine at preparation will not remove that person's time constraint. Resource assignments must match the claimed rate.

Quality affects useful output. If twelve inspected jobs include ten that pass on their first attempt, firstpass yield is ten divided by twelve, approximately 83.33 percent. This is distinct from equipment availability. If a planned eighthour period contains one and a half hours of downtime, time available is six and a half hours, or 81.25 percent. Neither measure alone establishes delivered output.

Choose a few measures tied to an actual decision. Track waiting time if jobs accumulate between stations, rework if defects recur, and missingpart delays if preparation repeatedly stops. Do not combine unlike measures into a reassuring average. The purpose of a board is to show the constraint clearly enough that an improvement can be tested and its effect observed.

min ‐ Minute. Time unit; the diagram’s min/item means minutes of processing per item.

Restore a useful service, then verify the next dependency

Rebuilding systems beyond the household

Units and terms in this account

= equals

min minute, 60 seconds

% percent, parts per hundred · = equals · ≈ approximately equal to