Throughput, first-item time and one-person work differ

Read the illustration’s labels

PREPARATION

15 min / item 4 per

hour

ASSEMBLY

30 min / item 2 per

INSPECTION

20 min / item 3 per

In the drawing: PREPARATION; 15 min / item 4 per hour; ASSEMBLY; 30 min / item 2 per hour; INSPECTION; 20 min / item 3 per hour

Bottleneck

Read the illustration’s labels

MODEL

RESULT

Independent stations

Steady-state limit: 2 items / hour

One item, no waiting

15 + 30 + 20 = 65 minutes

One worker, no overlap

60 / 65 ≈ 0.923 item / hour

First-pass quality

10 / 12 ≈ 83.33%

Time availability

6.5 / 8 = 81.25%

These are distinct measures. Do not average them into one claim.

In the drawing: MODEL RESULT; Independent stations Steady-state limit: 2 items / hour; One item, no waiting 15 + 30 + 20 = 65 minutes; One worker, no overlap 60 / 65 ≈ 0.923 item / hour; First-pass quality 10 / 12 ≈ 83.33%; Time availability 6.5 / 8 = 81.25%; These are distinct measures. Do not average them into one claim.

Original teaching drawing · Numerical examples are invented

Invented station times, independent staffing and no transfer losses. The one‐worker comparison and the first‐item processing time use different, explicitly stated models.

Capacity describes a rate under stated conditions. It should not be confused with the elapsed time of one job. In the invented line, preparation takes fifteen minutes per item, assembly thirty and inspection twenty. With independent adequately staffed stations, preparation can handle four items per hour, assembly two and inspection three. Assembly is the limiting station at two items per hour in this simplified steadystate calculation.

One item still needs sixtyfive minutes of processing across the three operations, before transfer or waiting time. The line does not complete the first item in thirty minutes merely because its steadystate bottleneck rate is two per hour. A diagram that reports only the fastestlooking number hides this distinction.

If one person performs all three operations, the relevant processing total is sixtyfive minutes per item. The idealized rate is sixty divided by sixtyfive, approximately 0.923 item per hour. Adding another machine at preparation will not remove that person's time constraint. Resource assignments must match the claimed rate.

Quality affects useful output. If twelve inspected jobs include ten that pass on their first attempt, firstpass yield is ten divided by twelve, approximately 83.33 percent. This is distinct from equipment availability. If a planned eighthour period contains one and a half hours of downtime, time available is six and a half hours, or 81.25 percent. Neither measure alone establishes delivered output.

Choose a few measures tied to an actual decision. Track waiting time if jobs accumulate between stations, rework if defects recur, and missingpart delays if preparation repeatedly stops. Do not combine unlike measures into a reassuring average. The purpose of a board is to show the constraint clearly enough that an improvement can be tested and its effect observed.

min ‐ Minute. Time unit; the diagram’s min/item means minutes of processing per item.

Restore a useful service, then verify the next dependency

Rebuilding systems beyond the household

A service is restored at the user’s end

The service record is presented as a selectable table in the related account · page 1637

Argentina: coordinate through actual operators and arrangements. No public-service authority is implied.

Choose the next job by consequence and feasibility

Decision fieldWhat it establishes
ConsequenceThe effect of delaying a service or repair.
ReadinessWhether specification, materials, access and authorization are available.
Resource conflictWhether proceeding consumes something reserved for a more urgent need.
Responsible personWho can act and communicate a change in status.
Review triggerA new finding, changed need or arrival of a missing dependency.

A priority list should explain why one job is being done before another. A simple numerical score can hide disagreement about what matters. Start with the consequences of leaving each service unavailable, the people affected, available alternatives and the time before conditions worsen. Then identify what can actually be completed with the current capabilities and dependencies.

The invented board compares three requests: restoring a noncritical tool bench, replacing an approved part in a service under its operator's control, and investigating an uncertain machine fault. Their labels do not determine priority by themselves. The service operator's need, the fault's consequence, the available alternative and the required competence decide the order. A dramatic machine should not automatically outrank a small task that restores an essential shared function.

Separate urgent from ready. An urgent task can still be blocked by an unknown specification or missing authorization. Mark the block and assign a person to resolve it. Meanwhile, a different ready task may proceed if it does not consume a resource reserved for the urgent work. This is a reasoned allocation, not an excuse to ignore the blocked need.

Use a short decision note: evidence available, decision taken, owner, next review and trigger for changing the decision. For example, a confirmed delivery delay may activate an already verified alternative. A failed inspection may stop the planned handover. Write those triggers before events become confusing.

After completion, compare the predicted benefit with the observed result. Did the action restore the promised service, merely improve one component, or reveal another dependency? Keep all three outcomes distinct. An honest partial result is more useful than a completed checkbox that hides continued unavailability. The next team needs the actual state of the system.

Units and terms in this account

min minute, 60 seconds

% percent, parts per hundred · = equals · ≈ approximately equal to