| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 2. Gate-side cabin Method M1 Its interior use is unconfirmed; budget a small arrival office only as a scenario. | 40 m² | $60.0k-120.0k | $600-2.4k |
| 3. Perimeter wall Method M1 Maintain drainage openings and fire-service access; do not assume a security rating. | 900 m | $180.0k-540.0k | $900-8.1k |
| 4. Internal access road Method M2 Separate walking and delivery movements where barns meet the road. | 3500 m² | $280.0k-560.0k | $2.8k-14.0k |
| 5. Utility workshop Method M4 Provide tool storage, extraction and an unloading area separate from guests. | 300 m² | $270.0k-540.0k | $2.7k-13.5k |
| 6. Service vehicles and yard Method M4 One pooled equipment allowance, not a count or valuation of depicted vehicles. | 1 set | $80.0k-250.0k | $4.0k-25.0k |
| 7. Equestrian barn and pen Method M5 Separate feed, tack and manure movements from the household entrance. | 350 m² | $210.0k-525.0k | $3.1k-15.8k |
| 8. Roof solar panels Method M7 Check roof capacity and shading; panel count does not establish output. | 30 kWdc | $60.0k-105.0k | $600-2.1k |
| 9. Livestock barn Method M5 Species and stocking remain decisions; clean water and manure access come first. | 160 m² | $96.0k-240.0k | $1.4k-7.2k |
Build equals the assumed quantity multiplied by its chosen unit allowance. Annual care covers the stated service and repair allowance; staff, utilities and replacement reserves are additional. These retained scenario figures are not current supplier quotes. USD means United States dollar; k means thousand and m after a dollar amount means million. Square metres measure area, metres measure length, ha means hectares, and kWdc means kilowatts of direct-current rated capacity. Keep these historical planning allowances separate from the newer dated animal-price records.
Forest-Edge Estate: Components
Items 10-17 of 17 | All quantities and prices below are scenario assumptions
| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 10. Poultry coop and run Method M5 Provide predator-resistant mesh, cleaning access and a dry covered feed store. | 80 m² | $20.0k-56.0k | $400-2.2k |
| 11. Fruit orchard Method M6 The label does not identify species; select trees using soil and climate data. | 0.5 ha | $7.5k-20.0k | $300-1.6k |
| 12. Vegetable gardens Method M6 Split irrigation into maintainable zones and reserve access between beds. | 1000 m² | $20.0k-60.0k | $800-4.8k |
| 13. Greenhouse complex Method M6 Ventilation, shade and drainage must be selected for the crop and climate. | 500 m² | $75.0k-250.0k | $1.5k-10.0k |
| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 14. Guest houses Method M3 Model three 200 m2 houses; confirm the actual count and gross floor areas. | 600 m² | $1.50m-3.00m | $15.0k-60.0k |
| 15. Main lodge Method M3 Define bedrooms, kitchen, laundry and plant spaces before choosing the envelope. | 700 m² | $1.75m-3.50m | $17.5k-70.0k |
| 16. Terraces and connecting paths Method M2 Provide step-free routes where required and drainage away from thresholds. | 700 m² | $28.0k-70.0k | $280-1.8k |
| 17. Forest edge and planted grounds Method M15 Retain selected trees only after an arborist and wildfire-access review. | 2 ha | $30.0k-100.0k | $1.2k-8.0k |
Forest-edge: inside the lodge
Worked room programme | Assumed 700 m2 gross lodge | Areas are planning inputs, not measured dimensions
A room schedule before a floor plan
Six bedroom suites, including bathrooms 210 m2
Living and dining rooms 120 m2
Kitchen, pantry and food preparation 70 m2
Study / office 25 m2
Laundry and domestic store 45 m2
Entrance and circulation 100 m2
Walls and structural allowance 80 m2
Plant and technical rooms 50 m2
Total 700 m2. At the chosen $2,500-5,000/m2 allowance, the lodge is $1.75m-3.50m. This is already item 15 in the Forest-Edge register; do not add it again.
What is included and what needs its own schedule
The building allowance includes ordinary foundations, frame, roof, enclosure, internal services, standard fixed joinery and finishes. Estate distribution, treatment, solar and access are separate numbered packages.
Record the kitchen appliance list, laundry equipment, furniture, mattresses, window coverings, communications and loose equipment room by room. Specialty finishes, artwork, commercial kitchens and exceptional foundations need separate quotations.
For each room record: purpose, occupants, area, moisture exposure, electrical loads, water and waste points, ventilation, finishes, accessibility, cleaning access and replacement route. Test how a failed water heater or large refrigerator can be removed.
Blueprint package to develop
Survey and levels; site and drainage plan; dimensioned floor plans; elevations and sections; foundation and structural sheets; roof and waterproofing details; electrical and plumbing layouts; ventilation calculations; door/window schedules; finishes, quantities and inspection points.
Forest-edge: guests, water and staffing
Three assumed 200 m2 guest houses | Worked calculations are planning examples
One guest-house programme
Two bedrooms 44 m2
Two bathrooms 16 m2
Living and dining 45 m2
Units and terms in this account
k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m² square metre, an area unit · m metre, a length unit
k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m² square metre, an area unit · ha hectare, 10,000 square metres · m (currency) million, 1,000,000 of the stated currency
m (currency) million, 1,000,000 of the stated currency
m (currency) million, 1,000,000 of the stated currency · L litre, a volume unit · = equals · FTE Full-time equivalent, a workload measure · USD United States dollar