Feature, method and purposeAssumed quantityBuild USDCare/year USD
14. Guest houses Method M3 Model three 200 m2 houses; confirm the actual count and gross floor areas.600 m²$1.50m-3.00m$15.0k-60.0k
15. Main lodge Method M3 Define bedrooms, kitchen, laundry and plant spaces before choosing the envelope.700 m²$1.75m-3.50m$17.5k-70.0k
16. Terraces and connecting paths Method M2 Provide step-free routes where required and drainage away from thresholds.700 m²$28.0k-70.0k$280-1.8k
17. Forest edge and planted grounds Method M15 Retain selected trees only after an arborist and wildfire-access review.2 ha$30.0k-100.0k$1.2k-8.0k

Forest-edge: inside the lodge

Worked room programme | Assumed 700 m2 gross lodge | Areas are planning inputs, not measured dimensions

A room schedule before a floor plan

Six bedroom suites, including bathrooms 210 m2

Living and dining rooms 120 m2

Kitchen, pantry and food preparation 70 m2

Study / office 25 m2

Laundry and domestic store 45 m2

Entrance and circulation 100 m2

Walls and structural allowance 80 m2

Plant and technical rooms 50 m2

Total 700 m2. At the chosen $2,500-5,000/m2 allowance, the lodge is $1.75m-3.50m. This is already item 15 in the Forest-Edge register; do not add it again.

What is included and what needs its own schedule

The building allowance includes ordinary foundations, frame, roof, enclosure, internal services, standard fixed joinery and finishes. Estate distribution, treatment, solar and access are separate numbered packages.

Record the kitchen appliance list, laundry equipment, furniture, mattresses, window coverings, communications and loose equipment room by room. Specialty finishes, artwork, commercial kitchens and exceptional foundations need separate quotations.

For each room record: purpose, occupants, area, moisture exposure, electrical loads, water and waste points, ventilation, finishes, accessibility, cleaning access and replacement route. Test how a failed water heater or large refrigerator can be removed.

Blueprint package to develop

Survey and levels; site and drainage plan; dimensioned floor plans; elevations and sections; foundation and structural sheets; roof and waterproofing details; electrical and plumbing layouts; ventilation calculations; door/window schedules; finishes, quantities and inspection points.

Forest-edge: guests, water and staffing

Three assumed 200 m2 guest houses | Worked calculations are planning examples

One guest-house programme

Two bedrooms 44 m2

Two bathrooms 16 m2

Living and dining 45 m2

Kitchen 18 m2

Laundry 8 m2

Storage 7 m2

Circulation and walls 42 m2

Plant allowance 20 m2

One house totals 200 m2. Three total 600 m2 and cost $1.50m-3.00m at the chosen building allowance. This is already item 14. Room areas establish a brief, not a construction layout.

A water example with stated limits

Assume 20 residents and guests using 120 litres/person/day indoors: 20 x 120 = 2,400 L/day, or 2.4 m3/day. Three days without refill would require 7.2 m3 before any other demand or unusable storage. These are chosen inputs, not a verified design standard.

Add separate measured allowances for staff, livestock, irrigation, cleaning, firefighting and losses. Then check source refill rate and seasonal reliability. Do not size the estate tank from the 7.2 m3 example alone.

Coverage is different from headcount

One continuously occupied post needs 8,760 coverage hours/year. If one employee supplies an assumed 1,800 rostered coverage hours, 8,760 / 1,800 = 4.87 FTE before additional relief. A six-person estate team cannot be assumed to provide this post plus every other job.

Annual review

Separate manager, grounds, housekeeping, agriculture, maintenance and security hours. Price actual wages and employer costs, then add contracts, energy, waste collection and renewal. Compare monthly actual costs with the budget and revise occupancy or services before costs become unmanageable.

FTE : Full-time equivalent A measure of staff workload. Two people each working half the full-time hours together supply one equivalent position.

Forest-edge estate: cost and operation

USD scenario, 19 October 2026 | Costs for one alternative estate | Exclusions prevent a complete project total

Construction scenario

Visible feature allowances $4.69m-10.00m

Proposed missing services $236.0k-906.0k

Priced works subtotal $4.92m-10.90m

Professional / permit allowance $590.7k-2.18m

Contingency on priced works $1.23m-4.36m

Scenario envelope, exclusions apply $6.74m-17.44m

Annual operating provision

Asset care and minor repairs $58.3k-285.1k

Staff: assumed 6 full-time equivalents $300.0k-540.0k

Utilities and operating energy $30.0k-90.0k

Renewal reserve, set aside $49.2k-218.0k

Funded annual subtotal $437.5k-1.13m

Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are additional.

Services proposed, not shown or verified

Units and terms in this account

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m² square metre, an area unit · ha hectare, 10,000 square metres · m (currency) million, 1,000,000 of the stated currency

m (currency) million, 1,000,000 of the stated currency

m (currency) million, 1,000,000 of the stated currency · L litre, a volume unit · = equals · FTE Full-time equivalent, a workload measure · USD United States dollar

k (currency) thousand, 1,000 of the stated currency · m (currency) million, 1,000,000 of the stated currency