Kitchen 18 m2

Laundry 8 m2

Storage 7 m2

Circulation and walls 42 m2

Plant allowance 20 m2

One house totals 200 m2. Three total 600 m2 and cost $1.50m-3.00m at the chosen building allowance. This is already item 14. Room areas establish a brief, not a construction layout.

A water example with stated limits

Assume 20 residents and guests using 120 litres/person/day indoors: 20 x 120 = 2,400 L/day, or 2.4 m3/day. Three days without refill would require 7.2 m3 before any other demand or unusable storage. These are chosen inputs, not a verified design standard.

Add separate measured allowances for staff, livestock, irrigation, cleaning, firefighting and losses. Then check source refill rate and seasonal reliability. Do not size the estate tank from the 7.2 m3 example alone.

Coverage is different from headcount

One continuously occupied post needs 8,760 coverage hours/year. If one employee supplies an assumed 1,800 rostered coverage hours, 8,760 / 1,800 = 4.87 FTE before additional relief. A six-person estate team cannot be assumed to provide this post plus every other job.

Annual review

Separate manager, grounds, housekeeping, agriculture, maintenance and security hours. Price actual wages and employer costs, then add contracts, energy, waste collection and renewal. Compare monthly actual costs with the budget and revise occupancy or services before costs become unmanageable.

FTE : Full-time equivalent A measure of staff workload. Two people each working half the full-time hours together supply one equivalent position.

Forest-edge estate: cost and operation

USD scenario, 19 October 2026 | Costs for one alternative estate | Exclusions prevent a complete project total

Construction scenario

Visible feature allowances $4.69m-10.00m

Proposed missing services $236.0k-906.0k

Priced works subtotal $4.92m-10.90m

Professional / permit allowance $590.7k-2.18m

Contingency on priced works $1.23m-4.36m

Scenario envelope, exclusions apply $6.74m-17.44m

Annual operating provision

Asset care and minor repairs $58.3k-285.1k

Staff: assumed 6 full-time equivalents $300.0k-540.0k

Utilities and operating energy $30.0k-90.0k

Renewal reserve, set aside $49.2k-218.0k

Funded annual subtotal $437.5k-1.13m

Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are additional.

Services proposed, not shown or verified

P1 Source investigation and supply: $30.0k-150.0k P2 Storage allowance, assumed 20 m3: $6.0k-16.0k P3 Treatment allowance: $20.0k-100.0k P4 Wastewater completion allowance: $20.0k-100.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k

Forest access before luxury finishes

The long service route links animals, food growing and accommodation. Keep manure, workshop deliveries and visitors on distinct daily routes. The image shows only one obvious entrance; a site review must test emergency access and wildfire evacuation.

Day and night responsibilities

Day: inspect access and water/energy alarms; handle deliveries; separate food, livestock and waste routes; complete scheduled maintenance. Night: check routes and gate release; shield lights; secure service areas; assign emergency contacts. This is not a 24-hour staffed security commitment.

Open prices: No additional labelled feature is unpriced, but the global exclusions still apply.

Forest-Edge Estate: Argentine Pesos

Retained scenario conversion

The original worksheet used ARS 1,540 per USD. ARS means Argentine peso and USD means United States dollar. All amounts in this table are millions of pesos, including annual care. These are dated planning allowances, not a current market quotation.

ComponentBuild / ARS millionCare / ARS million per year
1. Security gate30.800 to 92.4000.616 to 3.696
2. Gate-side cabin92.400 to 184.8000.924 to 3.696
3. Perimeter wall277.200 to 831.6001.386 to 12.474
4. Internal access road431.200 to 862.4004.312 to 21.560
5. Utility workshop415.800 to 831.6004.158 to 20.790
6. Service vehicles and yard123.200 to 385.0006.160 to 38.500
7. Equestrian barn and pen323.400 to 808.5004.851 to 24.255
8. Roof solar panels92.400 to 161.7000.924 to 3.234
9. Livestock barn147.840 to 369.6002.218 to 11.088
10. Poultry coop and run30.800 to 86.2400.616 to 3.450
11. Fruit orchard11.550 to 30.8000.462 to 2.464
12. Vegetable gardens30.800 to 92.4001.232 to 7.392
13. Greenhouse complex115.500 to 385.0002.310 to 15.400
14. Guest houses2,310.000 to 4,620.00023.100 to 92.400
15. Main lodge2,695.000 to 5,390.00026.950 to 107.800
16. Terraces and connecting paths43.120 to 107.8000.431 to 2.695
17. Forest edge and planted grounds46.200 to 154.0001.848 to 12.320

BUILD ENVELOPE ARS M 10,385.490 to 26,862.528 ANNUAL FUND ARS M 673.773 to 1,745.005

Totals include service/fee/contingency or staffing/reserve allowances beyond the rows. Unpriced items remain excluded.

Units and terms in this account

m (currency) million, 1,000,000 of the stated currency · L litre, a volume unit · = equals · FTE Full-time equivalent, a workload measure · USD United States dollar

k (currency) thousand, 1,000 of the stated currency · m (currency) million, 1,000,000 of the stated currency

ARS Argentine peso

BY-SA Creative Commons Attribution-ShareAlike