| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 12. Standby enclosure Method M10 Source label says backup generator; equipment type and rating are unverified. | 1 set | $25.0k-100.0k | $500-5.0k |
| 13. Battery storage Method M7 Specify usable energy, power, fire separation and emergency isolation. | 100 kWh | $60.0k-100.0k | $600-2.5k |
| 14. Solar array Method M7 Confirm grid arrangement and shading before sizing strings. | 60 kWdc | $120.0k-210.0k | $1.2k-4.2k |
| 15. Well and pump house Method M8 A drawn well proves neither yield nor drinking-water quality. | 1 set | $30.0k-150.0k | $600-6.0k |
| 16. Water storage Method M8 The 40 m3 budget quantity is assumed; reserve volume needs a demand study. | 40 m3 | $12.0k-32.0k | $120-640 |
| 17. Water filtration Method M8 Select treatment from accredited test results, not tank color. | 1 set | $20.0k-100.0k | $800-8.0k |
| 18. Orchard Method M6 Species, rootstock and spacing remain unverified. | 0.5 ha | $7.5k-20.0k | $300-1.6k |
| 19. Greenhouse Method M6 Set drainage and ventilation before placing beds. | 250 m² | $37.5k-125.0k | $750-5.0k |
| 20. Vegetable gardens Method M6 Keep crop irrigation separate from drinking-water distribution. | 900 m² | $18.0k-54.0k | $720-4.3k |
| 21. Chicken coop Method M5 Provide covered feed and cleaning access. | 60 m² | $15.0k-42.0k | $300-1.7k |
| 22. Chicken tunnels and runs Method M5 Model the run separately; mesh and footing depend on predator risk. | 80 m² | $20.0k-56.0k | $400-2.2k |
| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 23. Central island and planted grounds Method M15 Keep vegetation clear of approach sightlines and service routes. | 1.5 ha | $22.5k-75.0k | $900-6.0k |
Axial estate and growing grid: cost and operation
Construction scenario
Visible feature allowances $4.08m-8.77m
Proposed missing services $180.0k-640.0k
Priced works subtotal $4.26m-9.41m
Professional / permit allowance $511.1k-1.88m
Contingency on priced works $1.06m-3.76m
Scenario envelope, exclusions apply $5.84m-15.05m
Annual operating provision
Asset care and minor repairs $47.0k-239.2k
Staff: assumed 6 full-time equivalents $300.0k-540.0k
Utilities and operating energy $30.0k-90.0k
Renewal reserve, set aside $42.6k-188.2k
Funded annual subtotal $419.6k-1.06m
Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are
additional.
Services proposed, not shown or verified
P4 Wastewater completion allowance: $20.0k-100.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k
Utilities need protected working space
The rear service strip compresses food, water and energy systems. Establish clear equipment boundaries, maintenance routes and clean-water protection before reproducing this arrangement.
Day and night responsibilities
Open prices: No additional labelled feature is unpriced, but the global exclusions still apply.
Axial Estate And Growing Grid: Argentine Pesos
Retained scenario conversion
Units and terms in this account
k (currency) thousand, 1,000 of the stated currency · USD United States dollar · kWh kilowatt-hour, energy · ha hectare, 10,000 square metres · m² square metre, an area unit
m (currency) million, 1,000,000 of the stated currency · k (currency) thousand, 1,000 of the stated currency
ARS Argentine peso