Feature, method and purposeAssumed quantityBuild USDCare/year USD
12. Standby enclosure Method M10 Source label says backup generator; equipment type and rating are unverified.1 set$25.0k-100.0k$500-5.0k
13. Battery storage Method M7 Specify usable energy, power, fire separation and emergency isolation.100 kWh$60.0k-100.0k$600-2.5k
14. Solar array Method M7 Confirm grid arrangement and shading before sizing strings.60 kWdc$120.0k-210.0k$1.2k-4.2k
15. Well and pump house Method M8 A drawn well proves neither yield nor drinking-water quality.1 set$30.0k-150.0k$600-6.0k
16. Water storage Method M8 The 40 m3 budget quantity is assumed; reserve volume needs a demand study.40 m3$12.0k-32.0k$120-640
17. Water filtration Method M8 Select treatment from accredited test results, not tank color.1 set$20.0k-100.0k$800-8.0k
18. Orchard Method M6 Species, rootstock and spacing remain unverified.0.5 ha$7.5k-20.0k$300-1.6k
19. Greenhouse Method M6 Set drainage and ventilation before placing beds.250 m²$37.5k-125.0k$750-5.0k
20. Vegetable gardens Method M6 Keep crop irrigation separate from drinking-water distribution.900 m²$18.0k-54.0k$720-4.3k
21. Chicken coop Method M5 Provide covered feed and cleaning access.60 m²$15.0k-42.0k$300-1.7k
22. Chicken tunnels and runs Method M5 Model the run separately; mesh and footing depend on predator risk.80 m²$20.0k-56.0k$400-2.2k
Feature, method and purposeAssumed quantityBuild USDCare/year USD
23. Central island and planted grounds Method M15 Keep vegetation clear of approach sightlines and service routes.1.5 ha$22.5k-75.0k$900-6.0k

Axial estate and growing grid: cost and operation

Construction scenario

Visible feature allowances $4.08m-8.77m

Proposed missing services $180.0k-640.0k

Priced works subtotal $4.26m-9.41m

Professional / permit allowance $511.1k-1.88m

Contingency on priced works $1.06m-3.76m

Scenario envelope, exclusions apply $5.84m-15.05m

Annual operating provision

Asset care and minor repairs $47.0k-239.2k

Staff: assumed 6 full-time equivalents $300.0k-540.0k

Utilities and operating energy $30.0k-90.0k

Renewal reserve, set aside $42.6k-188.2k

Funded annual subtotal $419.6k-1.06m

Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are

additional.

Services proposed, not shown or verified

P4 Wastewater completion allowance: $20.0k-100.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k

Utilities need protected working space

The rear service strip compresses food, water and energy systems. Establish clear equipment boundaries, maintenance routes and clean-water protection before reproducing this arrangement.

Day and night responsibilities

Open prices: No additional labelled feature is unpriced, but the global exclusions still apply.

Axial Estate And Growing Grid: Argentine Pesos

Retained scenario conversion

Units and terms in this account

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · kWh kilowatt-hour, energy · ha hectare, 10,000 square metres · m² square metre, an area unit

m (currency) million, 1,000,000 of the stated currency · k (currency) thousand, 1,000 of the stated currency

ARS Argentine peso