Feature, method and purposeAssumed quantityBuild USDCare/year USD
16. Main residence Method M3 Confirm floor area and service rooms before cost refinement.900 m²$2.25m-4.50m$22.5k-90.0k
17. Grandparents' house Method M3 Use an accessible route that does not depend on decorative steps.350 m²$875.0k-1.75m$8.8k-35.0k
18. Parents' house Method M3 Keep service access clear of private gardens.350 m²$875.0k-1.75m$8.8k-35.0k
19. Guest villa Method M3 Define guest turnover and laundry demand.300 m²$750.0k-1.50m$7.5k-30.0k
20. Residential pools Method M11 Four pool packages are assumed for the cost comparison.4 set$240.0k-600.0k$7.2k-36.0k
21. Terraced landscaping and paths Method M15 Retaining structures are not priced until a level survey establishes them.3 ha$45.0k-150.0k$1.8k-12.0k

Terraced landscape estate: cost and operation

Construction scenario

Visible feature allowances $6.89m-14.48m

Proposed missing services $196.0k-706.0k

Priced works subtotal $7.09m-15.19m

Professional / permit allowance $850.7k-3.04m

Contingency on priced works $1.77m-6.07m

Scenario envelope, exclusions apply $9.71m-24.30m

Annual operating provision

Asset care and minor repairs $81.2k-382.8k

Staff: assumed 9 full-time equivalents $450.0k-810.0k

Utilities and operating energy $45.0k-135.0k

Renewal reserve, set aside $70.9k-303.7k

Funded annual subtotal $647.1k-1.63m

Terraced Landscape Estate: costs and responsibilities

All table amounts are millions of Argentine pesos; care is per year. Retained scenario: ARS 1,540 per USD. These are dated planning allowances, not current supplier quotations.

Component Build · ARS million Care · ARS million/year

ComponentBuild / ARS millionCare / ARS million per year
1. Estate entrance30.800 to 92.4000.616 to 3.696
2. Perimeter enclosure431.200 to 1,293.6002.156 to 19.404
3. Circulation road616.000 to 1,232.0006.160 to 30.800
4. Garage346.500 to 693.0003.465 to 17.325
5. Workshop346.500 to 693.0003.465 to 17.325
6. Trash system15.400 to 53.9000.616 to 4.312
7. Septic system30.800 to 154.0000.616 to 6.160
8. Water recycling30.800 to 154.0001.232 to 12.320
9. Solar parking structure308.000 to 539.0003.080 to 10.780
10. Carport canopy485.100 to 970.2004.851 to 24.255
11. Orchard18.480 to 49.2800.739 to 3.942
12. Organic gardens label46.200 to 138.6001.848 to 11.088
13. Greenhouse69.300 to 231.0001.386 to 9.240
14. Private lake labelUNPRICEDUNPRICED
15. Dock and lakeside pavilion86.240 to 221.7601.725 to 8.870
16. Main residence3,465.000 to 6,930.00034.650 to 138.600
17. Grandparents' house1,347.500 to 2,695.00013.475 to 53.900
18. Parents' house1,347.500 to 2,695.00013.475 to 53.900
19. Guest villa1,155.000 to 2,310.00011.550 to 46.200
20. Residential pools369.600 to 924.00011.088 to 55.440
21. Terraced landscaping and paths69.300 to 231.0002.772 to 18.480

Build envelope: ARS 14,956.372 to 37,420.768 million. Annual fund: ARS 996.472 to 2,512.587 million. Totals include service, fee and contingency or staffing and reserve allowances beyond the rows. Unpriced items remain excluded.

Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are additional. Proposed services, not verified: P1 Source investigation and supply: $30.0k-150.0k P2 Storage allowance, assumed 20 m³: $6.0k-16.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k Keep reuse water separate from drinking water. The illustration places multiple waste and water functions close to gardens and the lake. Resolve source protection, wastewater disposal and reserve areas before landscaping. Day and night responsibilities. Day: inspect access and water/energy alarms; handle deliveries; separate food, livestock and waste routes; complete scheduled maintenance. Night: check routes and gate release; shield lights; secure service areas; assign emergency contacts. This is not a 24-hour staffed security commitment.

Units and terms in this account

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · PV Photovoltaic · m metre, a length unit · m² square metre, an area unit · ha hectare, 10,000 square metres · m (currency) million, 1,000,000 of the stated currency

k (currency) thousand, 1,000 of the stated currency · m (currency) million, 1,000,000 of the stated currency · USD United States dollar · ARS Argentine peso

ARS Argentine peso

k (currency) thousand, 1,000 of the stated currency · m³ cubic metre, a volume unit · BY-SA Creative Commons Attribution-ShareAlike