| Feature, method and purpose | Assumed quantity | Build USD | Care/year USD |
|---|---|---|---|
| 15. Main residence Method M3 Define occupancy and room areas before structural design. | 900 m² | $2.25m-4.50m | $22.5k-90.0k |
| 16. Family villas Method M3 Budget two 350 m2 villas as an explicit scenario. | 700 m² | $1.75m-3.50m | $17.5k-70.0k |
| 17. Guest lodge Method M3 Check its shoreline setback and emergency approach. | 350 m² | $875.0k-1.75m | $8.8k-35.0k |
| 18. Swimming pool Method M11 Provide barriers, disinfection and separate pool drainage. | 1 set | $60.0k-150.0k | $1.8k-9.0k |
| 19. Lakeside pavilion Method M12 Check wind exposure and public access restrictions. | 100 m² | $100.0k-250.0k | $1.0k-7.5k |
| 20. Private dock label Method M12 A private label does not establish rights to use the lakebed. | 100 m² | $70.0k-180.0k | $1.4k-7.2k |
| 21. Lake Method M12 Acquisition, shoreline works and water rights are unpriced. | Unresolved | Unpriced | Unpriced |
| 22. Courts, paths and grounds Method M15 Maintain sightlines and tree access around the lodge. | 3 ha | $45.0k-150.0k | $1.8k-12.0k |
Dock and pavilion estate: cost and operation
Construction scenario
Visible feature allowances $6.47m-13.62m
Proposed missing services $196.0k-706.0k
Priced works subtotal $6.67m-14.33m
Professional / permit allowance $800.0k-2.87m
Contingency on priced works $1.67m-5.73m
Scenario envelope, exclusions apply $9.13m-22.93m
Annual operating provision
Dock and Pavilion Estate: costs and responsibilities
Component Build · ARS million Care · ARS million/year
| Component | Build / ARS million | Care / ARS million per year |
|---|---|---|
| 1. Entrance gate | 30.800 to 92.400 | 0.616 to 3.696 |
| 2. Boundary enclosure | 338.800 to 1,016.400 | 1.694 to 15.246 |
| 3. Access drive and forecourts | 492.800 to 985.600 | 4.928 to 24.640 |
| 4. Garage | 415.800 to 831.600 | 4.158 to 20.790 |
| 5. Barn | 231.000 to 577.500 | 3.465 to 17.325 |
| 6. Chicken coop and run | 38.500 to 107.800 | 0.770 to 4.312 |
| 7. Trash system | 15.400 to 53.900 | 0.616 to 4.312 |
| 8. Septic system | 30.800 to 154.000 | 0.616 to 6.160 |
| 9. Water treatment | 30.800 to 154.000 | 1.232 to 12.320 |
| 10. Battery storage | 110.880 to 184.800 | 1.109 to 4.620 |
| 11. Solar array | 184.800 to 323.400 | 1.848 to 6.468 |
| 12. Orchard | 13.860 to 36.960 | 0.554 to 2.957 |
| 13. Vegetable gardens | 30.800 to 92.400 | 1.232 to 7.392 |
| 14. Greenhouse | 69.300 to 231.000 | 1.386 to 9.240 |
| 15. Main residence | 3,465.000 to 6,930.000 | 34.650 to 138.600 |
| 16. Family villas | 2,695.000 to 5,390.000 | 26.950 to 107.800 |
| 17. Guest lodge | 1,347.500 to 2,695.000 | 13.475 to 53.900 |
| 18. Swimming pool | 92.400 to 231.000 | 2.772 to 13.860 |
| 19. Lakeside pavilion | 154.000 to 385.000 | 1.540 to 11.550 |
| 20. Private dock label | 107.800 to 277.200 | 2.156 to 11.088 |
| 21. Lake | UNPRICED | UNPRICED |
| 22. Courts, paths and grounds | 69.300 to 231.000 | 2.772 to 18.480 |
Build envelope: ARS 14,066.037 to 35,309.120 million. Annual fund: ARS 979.548 to 2,434.909 million. Totals include service, fee and contingency or staffing and reserve allowances beyond the rows. Unpriced items remain excluded.
Asset care and minor repairs $74.4k-349.5k Staff: assumed 9 full-time equivalents $450.0k-810.0k Utilities and operating energy $45.0k-135.0k Renewal reserve, set aside $66.7k-286.6k Funded annual subtotal $636.1k-1.58m Staff: $50k-90k per FTE/year, chosen loaded allowance. Utilities: $5k-15k per FTE/year as a coarse placeholder, not an energy calculation. Replace both with rosters and metered demand. Taxes, insurance, food, feed, aircraft and exceptional works are additional. Proposed services, not verified: P1 Source investigation and supply: $30.0k-150.0k P2 Storage allowance, assumed 20 m³: $6.0k-16.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k Protect the shore. The lower utility cluster is useful for deliveries, but sewage disposal, battery siting and crop areas need verified separation. The repeated poultry label is one operating zone. Day and night responsibilities. Day: inspect access and water/energy alarms; handle deliveries; separate food, livestock and waste routes; complete scheduled maintenance. Night: check routes and gate release; shield lights; secure service areas; assign emergency contacts. This is not a 24-hour staffed security commitment.
Units and terms in this account
k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m metre, a length unit · m² square metre, an area unit · kWh kilowatt-hour, energy · ha hectare, 10,000 square metres · m (currency) million, 1,000,000 of the stated currency
k (currency) thousand, 1,000 of the stated currency · m (currency) million, 1,000,000 of the stated currency · ARS Argentine peso
ARS Argentine peso
k (currency) thousand, 1,000 of the stated currency · m (currency) million, 1,000,000 of the stated currency · m³ cubic metre, a volume unit · BY-SA Creative Commons Attribution-ShareAlike