Feature, method and purposeAssumed quantityBuild USDCare/year USD
12. Lower vegetable beds Method M6 Reserve irrigation, wash and harvest circulation.1200 m²$24.0k-72.0k$960-5.8k
13. Main manor Method M3 Define room areas and occupancy before estimating energy and staffing.1400 m²$3.50m-7.00m$35.0k-140.0k
14. Sister's house Method M3 Identify independent utilities and maintenance access.400 m²$1.00m-2.00m$10.0k-40.0k
15. Parents' house Method M3 Review slopes, accessible entry and service routing.400 m²$1.00m-2.00m$10.0k-40.0k
16. Unlabelled residence Method M3 No family attribution is established for this building.400 m²$1.00m-2.00m$10.0k-40.0k
17. Barn and stables Method M5 Maintain separate feed, bedding and manure handling.600 m²$360.0k-900.0k$5.4k-27.0k
18. Horse arena Method M5 The area allowance is provisional; footing and drainage need design.1 ha$8.0k-20.0k$320-1.6k
19. Greenhouse village Method M6 Distinguish heated production from simple crop protection.1000 m²$150.0k-500.0k$3.0k-20.0k
20. Water treatment Method M8 Source chemistry and waste disposal control the treatment process.1 set$20.0k-100.0k$800-8.0k
21. Upper fuel and storage Method M10 Contain fuel and keep incompatible materials in separate stores.1 set$20.0k-80.0k$400-3.2k
22. Lower fuel and storage Method M10 Confirm whether the two labels describe separate installations.1 set$20.0k-80.0k$400-3.2k
23. Service shop and tractor garage Method M4 Price actual process equipment separately from the shell.700 m²$630.0k-1.26m$6.3k-31.5k
24. Solar farm Method M7 Model energy yield and interconnection before procurement.250 kWdc$500.0k-875.0k$5.0k-17.5k
Feature, method and purposeAssumed quantityBuild USDCare/year USD
25. Recreation pools Method M11 Two packages are assumed; the picture is not an asset survey.2 set$120.0k-300.0k$3.6k-18.0k
26. Formal fountain and courts Method M11 Provide drain-down and cleaning access.1 set$10.0k-40.0k$300-2.4k
27. Trees and grounds Method M15 The printed GPS/date/altitude is not verified survey provenance.6 ha$90.0k-300.0k$3.6k-24.0k

Sunset estate overview: cost and operation

Construction scenario

Visible feature allowances $9.65m-20.81m

Proposed missing services $196.0k-706.0k

Priced works subtotal $9.85m-21.52m

Professional / permit allowance $1.18m-4.30m

Contingency on priced works $2.46m-8.61m

Scenario envelope, exclusions apply $13.49m-34.43m

Annual operating provision

Asset care and minor repairs $112.9k-545.4k

Staff: assumed 16 full-time equivalents $800.0k-1.44m

Utilities and operating energy $80.0k-240.0k

Renewal reserve, set aside $98.5k-430.4k

Funded annual subtotal $1.09m-2.66m

P1 Source investigation and supply: $30.0k-150.0k P2 Storage allowance, assumed 20 m3: $6.0k-16.0k P5 Estate distribution and communications: $80.0k-240.0k P6 Fire-service water provision: $40.0k-150.0k P7 Site drainage beyond priced roads: $40.0k-150.0k

Resolve ambiguous labels before procurement

The source has duplicate fuel/storage labels and an unclear SPASH label. Its printed coordinates, altitude and date do not establish a real surveyed site. Keep uncertain installations out of approved specifications.

Day and night responsibilities

Open prices: Labelled SPASH system

SPASH : SPASH, printed system name The estate illustration prints this label. Its underlying words and the system’s specification remain unverified. ARS : Argentine peso The currency in which the local price, quote or exchange rate is recorded.

Units and terms in this account

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · ha hectare, 10,000 square metres · m² square metre, an area unit · m (currency) million, 1,000,000 of the stated currency

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m² square metre, an area unit · m (currency) million, 1,000,000 of the stated currency · ha hectare, 10,000 square metres

m (currency) million, 1,000,000 of the stated currency · k (currency) thousand, 1,000 of the stated currency · ARS Argentine peso