Feature, method and purposeAssumed quantityBuild USDCare/year USD
2. Perimeter enclosure Method M1 Review airside security and obstacle constraints with the aviation designer.1600 m$320.0k-960.0k$1.6k-14.4k
3. Apron and taxi access Method M2 Road rates are only a placeholder; aircraft pavement requires a dedicated design and quote.9000 m²$720.0k-1.44m$7.2k-36.0k
4. Hangar Method M13 PC-12 NGX is a source label, not a confirmed aircraft identification.1000 m²$1.20m-2.50m$12.0k-62.5k
5. Depicted aircraft group Method M13 Aircraft acquisition and operation are excluded pending an actual fleet selection.UnresolvedUnpricedUnpriced
6. Runway Method M13 Length, width, pavement, obstacles and certification cannot be inferred.UnresolvedUnpricedUnpriced
7. Garage Method M4 Keep road vehicles outside aircraft maneuvering areas.250 m²$225.0k-450.0k$2.2k-11.2k
8. Machine shop Method M4 Aircraft maintenance approval and equipment are separate from a general workshop.300 m²$270.0k-540.0k$2.7k-13.5k
9. Greenhouse Method M6 Check wildlife attraction and obstacle implications before retaining this location.500 m²$75.0k-250.0k$1.5k-10.0k
10. Solar farm Method M7 A glare and obstacle review may affect the siting.120 kWdc$240.0k-420.0k$2.4k-8.4k
11. Family house Method M3 Evaluate noise, runway safety areas and emergency access before retaining the house.800 m²$2.00m-4.00m$20.0k-80.0k
12. Parents' house Method M3 Residential siting needs aviation and planning review.350 m²$875.0k-1.75m$8.8k-35.0k
Feature, method and purposeAssumed quantityBuild USDCare/year USD
13. Brother's house Method M3 Do not adopt the pictured runway offset as a safe distance.350 m²$875.0k-1.75m$8.8k-35.0k
14. Swimming pool Method M11 Include barriers and assess potential wildlife attraction in airport planning.1 set$60.0k-150.0k$1.8k-9.0k
15. River and woodland edge Method M12 Flood, ecology and water rights need site investigation.UnresolvedUnpricedUnpriced
16. Unlabelled entrance buildings Method M1 Use as an assumed arrival office only after confirming function.60 m²$90.0k-180.0k$900-3.6k
17. Landscape strips Method M15 Tree height and growth must be included in an obstacle assessment.2 ha$30.0k-100.0k$1.2k-8.0k

Runway-adjacent estate: cost and operation

Construction scenario

Visible feature allowances $7.00m-14.55m

Proposed missing services $236.0k-906.0k

Priced works subtotal $7.24m-15.46m

Professional / permit allowance $868.3k-3.09m

Contingency on priced works $1.81m-6.18m

Scenario envelope, exclusions apply $9.91m-24.73m

Annual operating provision

Asset care and minor repairs $76.2k-365.3k

Staff: assumed 9 full-time equivalents $450.0k-810.0k

Utilities and operating energy $45.0k-135.0k

Renewal reserve, set aside $72.4k-309.1k

Funded annual subtotal $643.5k-1.62m

Units and terms in this account

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m metre, a length unit · m² square metre, an area unit · m (currency) million, 1,000,000 of the stated currency · ha hectare, 10,000 square metres

k (currency) thousand, 1,000 of the stated currency · USD United States dollar · m² square metre, an area unit · m (currency) million, 1,000,000 of the stated currency · ha hectare, 10,000 square metres